Georgia Power today marked another year of safe construction and significant milestones at the Vogtle nuclear expansion site. The new units are currently scheduled to go into service in June 2019 (Unit 3) and June 2020 (Unit 4) and the remaining projected customer rate impact is approximately 2.5 percent, an average of less than 1 percent per year through completion.
In addition, the company’s recent completion of the settlement process between the project co-owners (Georgia Power, Oglethorpe Power Corporation, the Municipal Electric Authority of Georgia and Dalton Utilities) and the project’s contractors (Westinghouse and CB&I) settles all claims previously in litigation with the contractors, reaffirms the current in-service dates, adds additional contractual protections and positions Westinghouse and its affiliates as the primary contractor over the project.
To view the multimedia release go to:
http://www.multivu.com/players/English/7464951-ga-power-project-vogtle/
Categories //
Miscellaneous
Added:
3237 days ago by
MultiVuVideos
Runtime: 9m16s | Views: 972 |
Comments: 1
Not yet rated |
|